Installation Technology of centrifugal Fan Unit

Jun 11, 2019

Since the unit's composition is different, the precision requirements are different, and the experience and method of the construction personnel are different, so the installation process of the unit is different. However, to sum up, a centrifugal blower unit must go through: personnel, machines and tools, from the arrival of the equipment to the installation site and put into production. Preparation of materials-machine out-box inspection-foundation release and disposal-equipment in place-preliminary leveling-(dead foot bolt grouting)-equipment disassembly and cleaning, Assembly and inspection-accurate leveling and correction-secondary watering of the base-matching equipment (wind, water, Oil)-final calibration leveling, oil system flushing, machine unit debugging, unit commissioning, delivery acceptance and other basic installation process.www.jnblower.com